JACKSON, Mich. (AP) - Consumers Energy says it's holding off on building a $750 million, 700-megawatt natural gas-fired power plant in Genesee County and is buying a 540-megawatt plant in Jackson.

The Jackson-based CMS Energy Corp. unit announced the moves Thursday.

The Thetford Township plant near Flint would have opened in 2017 to serve about 445,000 people. The project was expected to create 30 plant jobs and 600 construction jobs.

The DPC Juniper LLC plant in Jackson employs about 20 people. Consumers Energy plans to pay $155 million and take ownership in 2016.

MLive.com reports that the plant's owners sued the city of Jackson last summer, claiming it was improperly assessed and overtaxed. State tax records show DPC Juniper started withdrawing the lawsuit last week.

Powered by WorldNow
All content © Copyright 2000 - 2014 WorldNow and WLNS. All Rights Reserved.
For more information on this site, please read our Privacy Policy and Terms of Service.

Click Here to link to the FCC's public inspection file for WLNS-TV and Here to view the WLAJ-TV file. Persons with Disabilities who need assistance with issues relating to the content of this station's FCC public inspection file should contact: Teresa Morton- Program Director for WLNS and WLAJ at 517-372-8282. Questions or concerns relating to the accessibility of the FCC's public file system should be directed to the FCC at 888-225-5322, 888-835-5322 (TTY), or fccinfo@fcc.gov.